Subsea Wire Saw Operations — Norway

Precision
Wreck
Cutting

Wire saw cutting of ship wrecks, offshore structures and subsea infrastructure. Specialist operations for shipowners, P&I clubs and salvage companies — from Norwegian coastal waters to international deployments.

Request Project Assessment Capabilities
24/7
Operational readiness
20+
Years subsea experience
Wire Saw Wreck Cutting Subsea Pile Cutting Vessel Dismantling P&I Club Operations Offshore Structure Removal Salvage Support ROV-Assisted Operations Harbour Clearance Wire Saw Wreck Cutting Subsea Pile Cutting Vessel Dismantling P&I Club Operations Offshore Structure Removal Salvage Support ROV-Assisted Operations Harbour Clearance
What We Do

Core Capabilities

01
Wreck Wire Sawing

Controlled dismantling of sunken vessels using diamond wire saws. Cuts through steel hull plating, frames and structural members with precision — minimising environmental disturbance and enabling controlled lift operations.

Steel / Cast Iron / Alloy
02
Subsea Concrete Cutting

Wire saw cutting of reinforced concrete structures, bridge piers, quay walls and caissons below the waterline. Capable of cutting sections for controlled crane lifts or in-situ fragmentation.

Reinforced Concrete
03
Pile & Jacket Cutting

Removal of offshore piles, monopiles and jacket structures. Wire saw operations allow precise below-mudline cuts — meeting decommissioning requirements without explosive techniques.

Offshore Decommissioning
04
Harbour Clearance

Emergency and planned removal of obstructions in port fairways, berths and navigational channels. Fast mobilisation with specialist vessels and dive support for time-critical operations.

Emergency Response
05
ROV-Assisted Operations

ROV survey and inspection prior to wire saw deployment. Detailed site assessment, wire placement verification and real-time monitoring throughout cutting operations.

Survey / Inspection
06
Salvage Support

Integrated wire saw cutting as part of broader salvage operations. Works alongside crane barges, salvage tugs and wreck removal contractors — cutting to specification for lift plans and float-off operations.

Lift Plan Integration
Methodology

How We Operate

01

Project Assessment

Preliminary review of site conditions, structural data and operational constraints. We provide a written scope assessment and indicative cost range — typically within 48 hours of receiving documentation.

02

ROV Survey & Planning

Pre-operation ROV inspection to confirm structural condition, sediment levels and wire saw access points. Survey data informs the cut sequence and equipment configuration.

03

Wire Saw Deployment

Diamond wire rigged through the target structure by surface divers or ROV, depending on depth and conditions. Wire saw unit mounted on vessel or pontoon. Cutting commences under continuous monitoring.

04

Section Removal

Cut sections prepared for crane lift, tow-out or in-situ deposition as specified by the salvage plan. Full documentation and as-executed reporting provided on completion.

Technical Specifications
Wire Type Diamond wire, multi-strand
Material Steel, reinforced concrete, cast iron, alloy
Mobilisation Norway
Vessel Dykkeservice 5 + support craft
Diver Cert. IMCA / DNV approved
Geographic range Norway, North Sea, international
Base Kristiansand, Norway
Who We Work With

Industry Sectors

P&I Clubs
Hull Underwriters
Salvage Companies
Port Authorities
Coastal Administrations
Offshore Operators
Shipowners
Decommissioning Contractors
Navy & Coast Guard
Infrastructure Owners
Environmental Agencies
Crane & Lift Contractors
IMCA Compliant Diving operations
DNV Approved Dive personnel
StartBANK Certified contractor
ISO HSE Health & safety management
Proven Track Record

Case Studies

Emergency Salvage Late 2024 / Early 2025

Mo i Rana Deep Water Quay

A 70-tonne excavator and a 700-tonne barge had foundered and were blocking the entire construction area at Norway's new deep water quay. Using underwater wire saw cutting, the excavator was sectioned into six pieces and fully recovered within six days — allowing other contractors to resume work almost immediately. The barge was divided into two ~350-tonne sections with 36 tonnes of lift chains installed beneath the hull on the seabed.

Client: Rana Municipality & Norwegian Coastal Administration (Kystverket)
Wreck Removal Aug – Sep 2019

M/S Osfjord · Linesøya, Åfjord

The 469-tonne vessel grounded during storm «Knud» in September 2018. Following multiple failed re-floating attempts, BOA Management engaged Kristiansand Bygg AS to section the hull using diamond wire saws. The wreck was divided into six sections, each lifted aboard crane barge Boabarge 42 and transported to Fosen Gjenvinning for recycling — completed within 26 days. The project received international coverage in Teknisk Ukeblad, NRK and Professionell Demolering.

Client: BOA Management
Get in Touch

Request a Project Assessment

Direct Contact

Base
Kristiansand, Norway
For urgent wreck clearance or harbour obstruction, call directly. We maintain 24/7 operational readiness and can provide an initial project assessment within 48 hours of receiving site documentation.